This project was to improve and expand the sewer system along Buddingevej road in the Lyngby area of northern Copenhagen. A simultaneously-drilled split-level tunnel design is a major unique feature of this project. A more common challenge we’re facing is time pressure, with the client requiring minimum disruption around this busy city thoroughfare and supply issues at the outset requiring us to mobilise more crew members to get the project back on schedule.
We are constructing 8 tunnels total, at one point with two different machines tunnelling in two different directions from one shaft in order to work more efficiently. The HK AVN has finished its tunnels with the MTS machine working on the remaining two.
Kouwenberg Infra B.V. completed all of the engineering and supplied all tunnelling equipment for this project.